We have also decided to start getting stuff figured out so we can begin building our dream house next year. Here is our tentative timeline:
- This winter get the land appraised and in our name
- Late winter/early spring- go to the bank and apply for construction loan
- Spring/summer- finalize blue prints, dirt work, basement poured, well dug, septic tank installed, electricity ran
- Late summer/early fall- Have our house set on the basement, let settle
- And as soon as we can- move in and finish the basement!!
I am very excited to start planning. Our goal is to have it done in a year (and have all of our credit cards paid off by then- we are almost there!). It is going to be a ton of work- especially with me returning to work, doing the PRIDE stuff, going to school and giving as much attention to the kiddos as they crave. But, I have a feeling I can do it.